A bill that includes additional bonding authority for a University of Utah Health medical campus project hit with ballooning costs passed the legislature Wednesday.
A provision in
The University of Utah Board of Trustees approved a move to ask the legislature for more bonding at its Feb. 13 meeting, where hospital officials said the project's price tag had grown to about $855 million from $500 million.
Changes to the project as well as escalating construction and imaging equipment costs contributed to the hike, Chief Financial Officer Charlton Park told the board.
"The cost estimate changed dramatically, the scope of the project has also changed dramatically," he said. "There's been an increase in square footage within the overall project of over 165,000 square feet."
In response to emailed questions, Park's office said "the amount and timing of the sale of additional bonds will depend upon several factors including forecasted project costs, the financial position of University of Utah Hospitals and Clinics, and the potential impact of philanthropic efforts."
An initial $340.8 million of general revenue bonds were sold for the project as part of a $478.4 million Utah Board of Higher Education issue in 2022, according to the University of Utah's 2023
The project includes a multi-specialty outpatient health center, an emergency department and hospital west of Salt Lake City in West Valley City.
Construction is expected to begin later this year or in early 2025, according to a University of Utah Health spokeswoman.